Guntakal - Gulbarga FEDL status as on 13-07-15 :
I was checking the DOWN Line (GR - GTL) and the progress was almost simlilar on UP line as well.
[1] Except for MALM - MTU (11 km) entire stretch is Double.
[2] GTL - NLA (10 km) : Wired.
[3]...
more... NLA - NMLU (5 km) : Few ploes are not wired.
[4] NMLU - ASP (17 km): Wired.
[5] ASP - ESV (27 km) : Bottom Hook and bottom wire are not installed.
[6] ESV - KGL (8 km) : 30% of the section is not wired.
[7] KGL - KO (13 km) : Poles erected but hooks are not installed for 50% of the poles.
[8] KO - MALM (13 km) : Poles are not erected at EGU and MALM stations.
[9] MALM - MTU (11 km): Ground is leveled for Double Line. Nothing started on Electrification.
[10] MTU - MRC (7 km) : Poles erected but only 20% hooks are installed.
[11] MRC - RC (10 km) : Poles erected but only 40% hooks are installed.
[12] RC - YDLP (22 km): Wired.
[13] YDLS - KSN (3 km): Poles erected but only 50% hooks are installed.
[14] KSN - WADI (82km): Wired.
[15] WADI - GR (36 km): Poles erected and hooks are installed.